Weekend Report: Another busy one as we approach the month of May!
Teams of volunteers were busy both last Thursday and on Saturday on the restoration of the TH&B Caboose with the following accomplishments checked off as they push to be ready for our Doors Open weekend on May 25th and 26th:
- All inner and outer windows were completed
- Hardware cleaning was completed
- Fuse and train order racks were installed
- Internal electrics were completed with temporary light fittings in place
- Great mock up lettering decals were tested
- Cupola benches were permanently fitted
- Stripping of doors for the cupola lower cabinets was completed
- The doors under the cupola seats were all fitted and permanently installed.
- All internal walls have now have one coat of grey paint.
Posting by Russ Milland; Photo by Alex Ruppel
Click on the picture for a closer look!